Budget: $15.3 Million
Design & Construction Schedule:
- Programming Design: January 2020-March 2020
- Schematic Design, Design Development & Construction Documents: January 2021 – September 2021
- Utility Relocation: September 2021 - October 2021
- Phase 1 - Bulldog Arena/Lobby: September 2021 – November 2022
- Phase 2 - Lower Level Renovations: December 2021 – August 2022
- Phase 3 - Upper Level Renovations: August 2022 – November 2022