Budget: $12,500,000
Design & Construction Schedule:
-
- Programming: November 2019 - April 2021
- Design: April 2021 - November 2021
- Construction: December 2021 - September 2022
- Occupancy: October 2022
- Anticipated Data Center Relocation: March 2023
- Anticipated West Building Demolition: May 2023