Enterprise Technology Services

 Coverage Map

Zone/Location Target Date
Zone 1    
VAN-NE-O
HFE-SW-O
HFE-E-O
SWN-SE-O
CLK-SE-O
HAL-SW-O

07/2005
07/2005
07/2005
07/2005
07/2005
07/2005

COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE

Zone 2    
HAL-SE-O
TTF-SW-O
BUS-NE-O
TTF-E-O
PIC-S-O
SCA-O-O
SRC-E-O
ECA-C-O

08/2005
08/2005
08/2005
08/2005
08/2005
08/2005
08/2005
08/2005

COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE

Zone 3    
VFS-NE-O
BON-E-O
PEN-NE-O
PHA-W-O
CRA-SW-O
HEN-W-O
08/2005
08/2005
08/2005
08/2005
08/2005
08/2005
COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE
Zone 4    
MAS-N-O
GRN-BE-O
AUT-NE-O
SCI-E-O
ASC-EN-O
WIL-NW-O
KIR-E-0

09/2005
09/2005
09/2005
09/2005
09/2005
09/2005
09/2005

COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE

Zone 5    
WAR-SE-O
TRA-S-O
MER-S-O
MCN-E-O
BRO-E-O
09/2005
09/2005
09/2005
09/2005
09/2005
COMPLETE
COMPLETE
COMPLETE
COMPLETE
COMPLETE
Zone 6    
PEN-SW-O
WCA-RC-O
WCA-FC-O
09/2006
09/2006
09/2006
COMPLETE
COMPLETE
COMPLETE
Zone 7    
GEN-NW-O
SPO-NW-O
SPO-SE-O
10/2006
10/2006
10/2006
COMPLETE
IN-PROGRESS
IN-PROGRESS
Zone 8    
WIM-S-O 10/2006 COMPLETE

Project Notes:

  • 09/12/2005 - Six more canisters arrived for installation in Zone 5
  • 09/12/2005 - Zone 4 now has five canisters up and running. Looking at coverage areas to determine if CAR and SCI are needed
  • 08/29/2005 - Zones 1, 2, and 3 complete !! Finishing up final configurations of APs in Zone 4.
  • 08/15/2005 - Zone 3 has all canisters - awaiting final configuration
  • 08/15/2005 - Working on Zone 4 this week!!
  • 08/03/2005 - 9 access points in zones 1 and 2 are now live !!
  • 07/27/2005 - 3 access points live in the Quad area
  • 07/25/2005 - Consultants on-site to begin turning on access points
  • 07/05/2005 - Outdoor gateway systems arrive
  • 07/01/2005 - Mounting hardware arrives
  • 06/20/2005 - Contractors for power installation chosen
  • 06/15/2005 - PO issued for equipment